Mid-Valley Rehabilitation

Energy Efficiency

  • New Windows .30 U-value
  • Insulation C: (R-49) W (BIB R-21)
  • High Efficiency Heat Pump Installed
  • Sun Tunnels utilized for Daylighting
  • Duct Blast and Blower Door Testing completed

Sustainable Materials

  • Low VOC paint
  • Fiber-Cement siding with byproduct wood fiber

Indoor Air Quality

  • No VOC paint
  • No carpeting
  • Heat Recovery Ventilator
  • Rain screen
  • High volume range hood with make up air

The People

Owner: Mid-Valley Rehabilitation Center
Project Manager: John Mead
Interior Designer: Lisa Stonebridge, Design Alliance
Architect: James Ruggles

Certificate

  • Energy Star Rated

By The Numbers

4,584 – square feet, size of the two group homes combined

5 – months to complete project

10 – clients served with bedroom units

24 – number of grab bars installed in the four ADA bathrooms

832 – quantity of 2×4 studs utilized in staggered stud BIB insulated walls