Cozine One

Water Conservation

  • Low flow faucets
  • Low flow showers
  • Dual flush toilets

Energy Efficiency

  • 8″ thick double 2×4 walls with thermal breaks
  • Dense-pack blown in fiberglass insulation
  • Energy Star certified appliances
  • Raised heel trusses
  • Passive Solar Design

Sustainable Materials

  • Erosion control landscaping
  • Infill development within walking distance to downtown McMinnville
  • Job-site recycling

Indoor Air Quality

  • Spero low formaldehyde MDF trim (no added urea-formaldehyde)
  • Low VOC paint
  • Minimal carpeting
  • Heat Recovery Ventilato

Certificates

  • Energy Star
  • Earth Advantage

The People

Project Manager: John Mead
Community: Cozine Creek Cottages
Designer: m.o.daby design

By The Numbers

  • 94 – Major construction tasks from groundbreaking to completion
  • 8 – Months from project start to completion
  • 27 – Days spent framing the home
  • 43 – Days dedicated to interior finishes
  • 22 – Days building the foundation that supports it all